Construction progress

Month by month,
from site.

Real footage from Cape Point, as Platinum Tower rises.

Latest site update · 13 October 2026
Drone · 13 October 2026

Where the build is

  1. FoundationsDone
  2. StructureWe are here
  3. FacadeNext
  4. Fit-outNext
  5. HandoverNext

The build, month by month

  1. Latest

    October 2026

    Drone · 13 October 2026

    A full slab poured in a single day by three crews, over steel tied by hand. Behind it, the columns for the next level already stand.

  2. Platinum Tower on 28 September 2026: the ground floor framed in reinforced concrete, with column steel standing on the first slab

    September 2026

    On site · 28 September 2026

    The ground floor stands in reinforced concrete, with the first slab cast above it and column steel waiting for the next pour.

Every photograph and clip in this timeline was taken on site, on the date shown. None of them is a render.